Falling behind schedule on a federal construction project is one of those moments every contractor dreads. Suddenly, the pressure ramps up. Liquidated damages start looming, the COR is asking more questions, and every schedule update feels like it’s under a microscope. Delays can strain relationships, trigger disputes, and put future work at risk.
But being behind does not automatically mean the project is spiraling out of control. What really matters is what you do next. How you respond, document, and communicate after a slip can either rebuild confidence or raise more red flags. This is exactly where recovery schedules come into play — not as a formality, but as a practical tool to regain control, show intent, and demonstrate that the project is still being actively managed.
Start With the Right Mindset: Diagnose Before You React
When a project slips, the knee-jerk reaction is often to throw resources at it. Add overtime. Add crews. Compress activities. While those tactics can help in certain situations, jumping straight into “fix mode” without understanding the root cause often makes things worse.
Before touching the schedule, slow down and diagnose what actually happened.
Ask yourself:
- Is the delay excusable, such as weather impacts, differing site conditions, or government-caused issues?
- Is it non-excusable, like staffing shortages, subcontractor performance, or flawed sequencing?
- Is the delay affecting the critical path, or is it isolated to work with float?
- Has the baseline schedule been properly maintained and updated up to this point?
A recovery schedule built on bad assumptions or incomplete data won’t hold up under review. It may look aggressive on paper, but it won’t be believable or sustainable in the field.
What Recovery Schedules Really Are
There’s a lot of misunderstanding around recovery schedules on federal jobs.
A recovery schedule is not a re-baseline designed to erase past delays. It’s not a best-case fantasy with unrealistic durations. And it’s definitely not something you throw together just to satisfy a government request.
A real recovery schedule is a transparent, logic-driven plan that shows how you intend to regain lost time. It demonstrates that you understand the problem, that you’re in control of the work, and that you’re actively managing risk.
On federal projects, recovery schedules are often requested when performance concerns already exist. That means they’re going to be reviewed closely by schedulers, CORs, and sometimes claims consultants. Credibility matters.
Step One: Make Sure the Current Schedule Reflects Reality
Before you can recover anything, your current schedule update has to be solid.
That means:
- Actual start and finish dates that match what’s really happened in the field
- Honest remaining durations, not wishful thinking
- Clean logic with no open ends, excessive constraints, or artificial float
- A clearly defined critical path that makes sense
If the current schedule can’t be trusted, the recovery schedule won’t be either. No amount of acceleration will matter if the foundation is flawed.
Step Two: Identify Recovery Strategies That Make Sense
Once you clearly understand where the project stands, you can start looking at realistic ways to recover time. Not every project needs every strategy, and not every delay can be fully recovered.
Common recovery approaches include:
Resequencing work. In some cases, activities that were originally planned sequentially can be overlapped. Federal specs can be rigid, but there are often opportunities if you coordinate closely and get proper approvals.
Adding resources. Additional crews, specialty subcontractors, or extended shifts can help shorten durations, but only if productivity assumptions are realistic. Simply doubling manpower doesn’t always double output.
Selective overtime. Overtime can be effective in short bursts, but long-term reliance often leads to fatigue, safety concerns, and declining productivity. It should be used strategically, not as a blanket solution.
Changing means and methods. Prefabrication, alternative installation techniques, or different equipment can sometimes unlock real schedule gains that manpower alone can’t achieve.
Focusing on the true critical path. This is where many contractors go wrong. Accelerating non-critical work doesn’t move the completion date. Recovery efforts should be targeted only where they actually matter.
Step Three: Build the Recovery Schedule With Transparency
A strong recovery schedule clearly shows:
- What caused the delay
- What specific changes are being made to recover time
- How those changes impact logic, durations, and resources
- Whether full recovery is achievable or only partial mitigation
Trying to hide delays by deleting logic, manipulating float, or shortening durations without justification almost always backfires. Government reviewers are experienced, and those tactics are easy to spot.
If full recovery isn’t possible, say so. An honest, achievable plan to mitigate delay is far more effective than an aggressive promise you can’t keep.
Step Four: Make Sure the Plan Works Beyond the Schedule
Recovery schedules don’t exist in isolation. They affect cost, staffing, safety, and quality.
Before submitting or presenting the plan, ask:
- Does this approach align with the project budget?
- Can we realistically staff this plan given current labor conditions?
- Have safety and quality risks been addressed?
- Are subcontractors on board with the revised sequencing and expectations?
On federal projects, an aggressive schedule that introduces unmanaged risk can quickly become a bigger problem than the original delay.
Step Five: Communicate Early and Keep Communicating
A recovery schedule is as much about communication as it is about planning.
Walk the government through the logic. Clearly separate excusable and non-excusable delays. Document assumptions and constraints. Update the recovery schedule regularly and show whether the plan is working.
Proactive, transparent communication goes a long way in maintaining trust, even when performance has slipped.
Common Pitfalls to Avoid
Many federal contractors run into trouble by:
- Re-baselining without approval
- Ignoring contract scheduling requirements
- Letting schedule updates fall behind
- Over-accelerating and burning out crews
- Treating the recovery schedule as a one-time submission instead of an ongoing process
Recovery isn’t a document you submit once. It’s an active management effort.
Being behind schedule doesn’t define your project. How you respond does. A well-built recovery schedule shows that you understand the situation, have a realistic plan, and are taking your contractual responsibilities seriously. In the federal world, that level of credibility can be just as valuable as the days you’re trying to recover.